Saturday, May 30, 2026
Week 3 of the NOMADS project at Mingus Mountain Camp and Retreat was a push to the end for everyone. Those working to repair and improve the men’s bathroom completed that task Wednesday afternoon.
It was everyone working on the Camp Store on Thursday. Wednesday had been an extremely windy day and high winds were predicted for Friday. We really needed to get the tin roofing installed but Wednesday we couldn’t safely manage the tin in the 40mph winds. We decided to give it a try first thing Thursday morning and God answered our prayers. The winds remained manageable and we safely completed the roofing about 10:00 am Thursday. After that, we painted the store, installed shelving and cleaned up the construction debris. We didn’t quite complete the painting on Thursday but two of our members were staying until the first of the week and they completed the second coat of paint on Saturday.
Below is a list of all the projects completed by NOMADS the past three weeks. It was another successful project and the Camp Director seemed very pleased.